The 25 projects worth $17b to Queensland

TWENTY-five projects worth $17 billion and creating tens of thousands of jobs have been listed in the Building Queensland Infrastructure Pipeline, the State Government's blueprint for what it reckons should be investigated and built in our state.

The projects - all costing $50 million or above - include new hospitals and renovations, extra schools, upgrading the Bruce Highway and M1, the massive $2.1 billion Brisbane Live entertainment precinct, dredging Gladstone Port for bigger ships, a congestion-busting motorway bridge, dams and water pipelines.

But while State Development Minister Cameron Dick is crowing about the 40,000 jobs he says the Palaszczuk Government is delivering, the LNP Opposition say the report highlights delays and inaction, including for the biggest project listed - the massive $2.1 billion Brisbane Live.

The LNP says the massive revamp of Roma St to include a world class entertainment precinct and 17,000 to 18,000 capacity arena has been in the languishing in the hands of the Palaszczuk Government without a decision.

Artists impressions of the Brisbane Live precinct in Brisbane that would transform the area around the Roma Street Station
Artists impressions of the Brisbane Live precinct in Brisbane that would transform the area around the Roma Street Station

Brisbane Live is one for four major projects where the business cases have been finished and are awaiting a decision, Building Queensland says in the pipeline report.

The other projects are the $247 million congestion-busting Centenary Bridge upgrade, the $90m-$100 million Lake Macdonald Dam improvement and the $70 million southwest pipeline bulk water connection to Beaudesert.

Building Queensland's Infrastructure Pipeline Report says Brisbane Live would be part of the Cross River Rail station at Roma Street and revitalise an "underutilised section of the Brisbane CBD".

"Capitalising on the existing range of sporting, music and arts events occurring in Brisbane, the Brisbane Live Entertainment Arena, with state of the art facilities and technology would provide Brisbane and Queensland with a world class facility for premium live events that is highly accessible and well connected to all transport networks," the report says.

It is expected to include 17,000 to 18,000 seat arena for events on a large deck structure built over the railway between Albert and Roma streets.

LNP Shadow Infrastructure Minister Andrew Powell said the report proved delays were bogging down desperately needed projects.

"Whether it was infrastructure for schools, dams or rail lines, projects across the board have been delayed, postponed or canned altogether," Mr Powell said.

"Our roads are congested, our schools are overcrowded, our hospitals are at breaking point and prisons overflowing all thanks to Annastacia Palaszczuk's failure to show any leadership.

"With infrastructure cuts and major project delays it's no wonder why Queensland has had the worst or second worst unemployment rate in the nation for most of the past 12 months."

The State Government received the Brisbane Live final report in November last year and would consider the project "in due course" but could not give a timeframe.

The Centenary Motorway is one of the busiest roads in Brisbane and needs a new bridge to cope with population growth according to Building Queensland. Picture: Chris McCormack
The Centenary Motorway is one of the busiest roads in Brisbane and needs a new bridge to cope with population growth according to Building Queensland. Picture: Chris McCormack

The State Government received the final reports for the Centenary Motorway bridge in June this year, and had sent it to Infrastructure Australia.

The water pipeline was received in March and more work is being done to make sure it provided value for money, he said.

State Development Minister Cameron Dick said the 2019 Infrastructure Pipeline Report demonstrated the significant progress made towards the state's infrastructure needs and creating more jobs.

"The next four years will see a $49.5B infrastructure investment across Queensland, including $12.9B over the next 12 months, which will support up to 40,500 local jobs," Mr Dick said.

"We are delivering more infrastructure than the LNP ever did.

"Sixty per cent of this year's infrastructure budget is being invested outside Greater Brisbane, where it will support around 25,500 jobs.

The Bruce Highway will get $12b for desperately-needed upgrades. Picture: Lachie Millard
The Bruce Highway will get $12b for desperately-needed upgrades. Picture: Lachie Millard

"Our strong infrastructure program underpins and unlocks private sector investment, making our state's $147 billion combined public-private infrastructure pipeline the second largest in Australia, according to Deloitte Access Economics.

"A strong, sustainable infrastructure pipeline provides confidence and certainty for investors, employers, businesses and communities.

"Projects in the pipeline respond to challenges associated with Queensland's growing and ageing population, like planning for revitalised Toowoomba and Bundaberg hospitals and improvements to the M1."

CONFIRMED PROJECTS


 

ON THE CARDS

Waiting for State Government consideration:

$2.1B BRISBANE LIVE ENTERTAINMENT ARENA

A new arena of 17,000 to 18,000 seats located on a large deck structure built over railways, roads and property, bounded by Albert Street to the north and Roma Street to the south. It would include new public spaces and facilities and active transport connections with neighbouring central business district locations.

 

An artist’s impression of the Brisbane Live precinct.
An artist’s impression of the Brisbane Live precinct.

$247M CENTENARY BRIDGE UPGRADE

The Centenary Motorway has progressively developed from a two-lane local arterial to an urban motorway; however, it has not kept up with the rapidly changing land use and

demographic changes. As a result, the strategic network is vulnerable to severe impacts on network performance and flow breakdown in the event of a traffic incident.

The detailed business case investigated the construction of a new three-lane northbound bridge and rehabilitation works for the existing bridges.

$90M-$100M LAKE MACDONALD DAM IMPROVEMENT PROJECT

The proposed upgrade will reduce dam safety risks by increasing the spillway capacity of the dam while maintaining water supply security.

$70M SOUTH WEST PIPELINE

Connecting the Beaudesert water supply zone with the South East Queensland water grid, via Logan City Council infrastructure. The bulk water pipeline is proposed to be approximately 24 kilometres in length, connecting the Beaudesert Water Treatment Plant storage reservoirs to the Flagstone development area and to the Water Grid pipeline network.

 

Detailed business case being completed:

$450M-$750M TOOWOOMBA HOSPITAL REDEVELOPMENT

Toowoomba Hospital is operating at capacity in a number of areas and the hospital faces long

emergency department waiting times and overcrowding. Forecast demand, driven by a growing and ageing population and high levels of chronic disease, is expected to place further pressure on the hospital.

The proposal is investigating a staged relocation of healthcare services to the Baillie Henderson Hospital site in Cranley Street which is 6.5 kilometres north of the existing hospital.

$430M SUNSHINE MOTORWAY-MOOLOOLAH RIVER INTERCHANGE

The existing Sunshine Motorway, Nicklin Way and Kawana Way transport infrastructure is congested and lacks capacity for forecast traffic growth. Proposed works include a new direct connection to the Sunshine Coast University Hospital precinct via a new two-lane road connecting Kawana Way at Parrearra and crossing the Mooloolah River to the planned Mooloolah River interchange.

 

 

Gladstone Port will benefit from dredging of the Clinton channel. Picture: Lachie Millard
Gladstone Port will benefit from dredging of the Clinton channel. Picture: Lachie Millard

$65M-$80M PORT OF GLADSTONE DREDGING

Dredging to widen the Clinton channel for bigger ships.

IPSWICH EXTRA PRIMARY SCHOOL CAPACITY - COST TO BE DETERMINED

Enrolment forecasts indicate that it is unlikely the schools currently serving the Ipswich City Council area will be able to accommodate future growth or alleviate pressure on the

existing state schools.

LOGAN EXTRA PRIMARY SCHOOL CAPACITY - COST TO BE DETERMINED

Existing schools in the area are reaching capacity and demand is predicted to increase significantly within the next five years.

EXTRA SPECIAL SCHOOLING CAPACITY ACROSS SEQ - COST TO BE DETERMINED

A number of special schools in South East Queensland have experienced significant growth in enrolments over the past five years. Population forecasts indicate that enrolments will likely

increase for students with special educational needs within the short to medium term as the population in South East Queensland continues to grow.

 

 

Bundaberg Hospital has been earmarked for a major upgrade.
Bundaberg Hospital has been earmarked for a major upgrade.

BUNDABERG HOSPITAL REDEVELOPMENT - COST TO BE DETERMINED

Bundaberg Hospital is having to send patients to other services to deal with demand.

PARADISE DAM IMPROVEMENT PROJECT - COST TO BE DETERMINED

The project will ensure the dam meets national and Queensland guidelines on dam safety standards and continues to function safely during extreme weather events.

SOMERSET DAM IMPROVEMENT PROJECT - COST TO BE DETERMINED

Built on the Stanley River between 1937 and 1959 to the engineering standards at that time, the dam now requires upgrading to comply with the provisions of the Australian

National Committee for Large Dams (ANCOLD) and Queensland guidelines on acceptable flood capacity in response to updated climate modelling for extreme weather events.

 

Preliminary business case:

GOLD COAST RAIL LINE CAPACITY IMPROVEMENT - KURABY TO BEENLEIGH - COST TO BE DETERMINED

The current track of the Gold Coast Rail Line between Kuraby and Beenleigh is limiting the ability for express trains to effectively pass all stops during peak periods. This is limiting the capacity of the corridor and impacting on service reliability.

PRINCESS ALEXANDRA HOSPITAL REHABILITATION AND SUBACUTE SERVICE RENEWAL - COST TO BE DETERMINED

The need for an infrastructure upgrade at the Princess Alexandra Hospital has been identified to provide contemporary fit-for-purpose facilities for statewide spinal cord and brain injury rehabilitation, as well as general rehabilitation services.

 

Strategic business case:

M1 Pacific Motorway - Daisy Hill to Loganholme

M1 Pacific Motorway - Loganholme to Nerang (including Coomera Connector)



REVEALED: Student to teacher ratios in our classrooms

premium_icon REVEALED: Student to teacher ratios in our classrooms

Coffs Coast schools with most crowded and best resourced classrooms.

'Cult' leader issues 'unreserved' apology to blogger

premium_icon 'Cult' leader issues 'unreserved' apology to blogger

UM leader brought a defamation case against a blogger in 2015

Belgian backpacker search officially called off

premium_icon Belgian backpacker search officially called off

"Trust me, they are not ready to stop"